During this phase of construction, a portion of southbound Interstate 5 (I-5) will be realigned and expanded into the Mexico El Chaparral Port of Entry
Construction work on southbound I-5 begins mid-September 2017
Realignment will be completed in the summer of 2019
This phase expands the number of southbound vehicle inspection lanes from five to 10 within the Port, and from 10 to 19 at the El Chaparral border crossing
Improves the roadway alignment for vehicles entering Mexico
An additional eight 8 northbound vehicle inspection lanes with 15 additional inspection booths are also being constructed
All pedestrian facilities will remain open during construction
Public Transportation
Public transit services (bus and trolley) will operate on a normal weekend schedule during the September shutdown
Southbound border crossers can ride public transit (bus and trolley) to access San Ysidro Port of Entry via the UC San Diego Blue Line or Route 906/907, or Otay Mesa via Routes 905 and 950 (from Iris Ave. Transit Center).
For more information on public transportation options, visit the San Diego MTS website.